Previous Civil Engineering Projects
|
(Infrastructure Phase 1) job required to advance roads and sewers for future development, job value: £1520k plus construction of drainage swales.
|
Approx 1500 square metres of carriageway were constructed at Kingsmead South (Infrastructure Phase 2) (blacktop & blockwork) including drainage and street lighting.
Job value: £568k |
Leisure Route refurbishment; a beauty spot in Milton Keynes, the job involved resurfacing, reconstructing and rebuilding sections of leisure routes and steps. A total area of approximately 14650 square metres.
Job value: £79k |
Involved the excavation of ponds, installation of a waterproof lining and topsoiling, erecting amphibian fencing and construction of leisure path.
Job value £109k |
|
Construction of cycleways at Hazeley, Milton Keynes including French drains, road crossings and street lights.
Job value: £228k |
Similar works were completed for the development of a redway at Willen Park, Milton Keynes with the addition of timber fencing.
Job value: £189k |
At Enterprise Lane, Campbell Park, Milton Keynes we imported fill to embankments, constructed blockwork access roads, surface drainage, service ducts, lighting and signs.
Job value: £206k |
Continuing our work in this area at Campbell Heights, Campbell Park, Milton Keynes we provided landscape works, re-grading to new levels, constructing leisure paths and redways, parking bays in blockwork and topsoiling to finish.
Job value: £194k |
Previous Groundwork Projects
|
Similar services were utilized during construction of Walnuts Special School, Milton Keynes in 2007. Job value:£520k and Drayton Park Combined School, Milton Keynes
Job value: £409k. |
At Hazeley Secondary School, Milton Keynes we provided bulk earthworks, substructures, foul drainage, surface water drainage (SUDS system), external services and hard pavings.
Job value:£2260k.
|
A commercial development of warehouses for Integra MK at Linford Wood, Milton Keynes involved all internal and external drainage works including Qmax system and flow control chambers; blockwork to access roads and parking areas.
Job value:£1170k. |
For an office development at Arena Park, Bletchley Milton Keynes we acquired the tender to construct strip and pad foundations, all internal and external drainage, block work to parking areas and bituminous surfacing to access roads.
Job value: £300k. |
|
Project Byron, Knowlhill, Milton Keynes: we provided bulk earthworks, substructures, external works, drainage, external services and section 278 works
Job value: £389k. |
At Linford Wood, Small Business Park, Milton Keynes we provided bulk earthworks, substructures, drainage, service trenches/ducts and pavings.
Job value: £1062k.
|
200 houses developed in Leadenhall, Milton Keynes we provided bulk earthworks, substructures, drainage, external services, roads and pavings.
Job value: £1682k |
Completion of flag paving and block work including features to the underground car park for ‘Jury’s Inn’ and the ‘Ramada Hotel’.
Job valued at £910k. |
|
Adoptable works completed for Bowmer & Kirkland, english Partnerships and Avebury among others.
Approx job value 2007: £46k |
The prestigious development known as ‘The Hub’ in Central Milton Keynes was officially opened by HRH Queen Elizabeth in 2007. We successfully completed external works including access roads, parking bays; piling mats and muck away for the ‘Jurys Inn’ and ‘Ramada Hotel’ together with constructing drainage diversion and internal drainage.
Job value: £700k. |
|
News Update
From Smith Construction Group Ltd
Finding Reputable Construction Companies Newport Pagnell
How to Choose Skip Hire Milton Keynes
Information About Recycling Milton Keynes and Construction
Inside View
From Smith Construction Group Ltd
Following the MK Dons
Sad to see you go..
|